The scope of work included; sewerage system, TSE/ Irrigation Water, Potable Water, Fire Main. The sewerage comprised a network of approximately 12km of network, ei pipe work, manhole, chambers, discharge, washout chambers, pumping stations (4) associated valve chambers (4) and MCC panels.
The sewerage system runs 3/4 of the way around the crescent eastwards from Jebel Ali Island, to the STP on plot GG on Dubai Land Island as a pumped/ gravity system, and from the end of plot Dubai to ploy GG as a gravity only system.
The system can be divided into 5 sections as follows; Jebel Ali Island, Main Crescent West, Atlantis Main Crescent West, Atlantis Main Crescent East, Atlantis-Dubai Land.